Morningside D & E Neighborhood Roadway Reconstruction

Share Morningside D & E Neighborhood Roadway Reconstruction on Facebook Share Morningside D & E Neighborhood Roadway Reconstruction on Twitter Share Morningside D & E Neighborhood Roadway Reconstruction on Linkedin Email Morningside D & E Neighborhood Roadway Reconstruction link

Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project began construction in 2022 and will continue in 2023. The work includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter and sidewalk,
  • Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
  • Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
  • Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit

Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project began construction in 2022 and will continue in 2023. The work includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter and sidewalk,
  • Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
  • Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
  • Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit
  • Turf Restoration Update – 6/25/24

    Share Turf Restoration Update – 6/25/24 on Facebook Share Turf Restoration Update – 6/25/24 on Twitter Share Turf Restoration Update – 6/25/24 on Linkedin Email Turf Restoration Update – 6/25/24 link

    West 42nd Street, Morningside Road, Grimes Avenue south of Morningside Road


    Supplemental turf restoration work is scheduled to begin as soon as 6/26, weather permitting, including:

    • If necessary, topsoil will be added to fill in low spots.
    • Seeding and hydromulch
    • Watering
    • Tips for growing green grass can be found here.


    The City will continue working with the contractor this summer to ensure the City’s specifications are met, including proper turf growth without significant weeds.

    As necessary following turf restoration, herbicide may be applied to resolve weed issues in the City right of way in front of your home.

    Thank you for your patience as we navigate the extremely wet start to the spring and summer.

  • Spring Work Resumes

    Share Spring Work Resumes on Facebook Share Spring Work Resumes on Twitter Share Spring Work Resumes on Linkedin Email Spring Work Resumes link

    The Contractor resumed work in May and is scheduled to conclude by the end of June.

    • Landscaping replacement began
    • Tree replacement began
    • Irrigation repairs began
    • Turf Restoration work is scheduled to begin soon.
      • If necessary, topsoil will be added to fill in low spots.
      • Seeding and hydromulch
      • Watering
      • Tips for growing green grass can be found here.


    Turf restoration was scheduled to begin the week of 5/20, but the location where the contractor purchases topsoil is exposed to weather and is wet from rain. Topsoil needs to be loose and friable during placement. Otherwise, it clumps together and increases the risk of over compaction, minimizing the seed’s ability to properly germinate. Thank you for your patience.

  • Nina Bonanno - Updated Contact Info

    Share Nina Bonanno - Updated Contact Info on Facebook Share Nina Bonanno - Updated Contact Info on Twitter Share Nina Bonanno - Updated Contact Info on Linkedin Email Nina Bonanno - Updated Contact Info link

    Updated contact info for Nina Bonanno, onsite project manager, can be found here. Stay tuned for updates on:

    • Remaining Irrigation repairs
    • Topsoil regrading, seeding and hydromulch touch ups as necessary. The seeded areas will be monitored throughout the spring to ensure proper turf establishment.
    • Replacement tree and landscape plantings.
  • Construction Substantial Completion Update

    Share Construction Substantial Completion Update on Facebook Share Construction Substantial Completion Update on Twitter Share Construction Substantial Completion Update on Linkedin Email Construction Substantial Completion Update link

    The project is now considered substantially complete. The contractor will address the following remaining items in the spring of 2024.

    • Sanitary sewer lining (winter)
    • Remaining Irrigation repairs
    • Topsoil regrading, seeding and hydromulch touch ups as necessary. The seeded areas will be monitored throughout the spring to ensure proper turf establishment.
    • Replacement tree and landscape plantings.
    • Warranty repairs

    The sidewalk snow and ice removal is the responsibility of the property owner.

    The City of Edina and GMH Asphalt thank you for your patience and cooperation throughout the 2023 construction season.

  • Construction Update - 11/9/2023

    Share Construction Update - 11/9/2023 on Facebook Share Construction Update - 11/9/2023 on Twitter Share Construction Update - 11/9/2023 on Linkedin Email Construction Update - 11/9/2023 link

    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

    • The final layer of asphalt pavement is complete.


    Project Wide

    • Select pavement striping and permanent signs are scheduled to be installed the week of 11/13.
    • Sanitary sewer lining is scheduled to be completed after Thanksgiving.
    • Replacement of landscaping items impacted by construction is complete except for a few properties.
      • Due to the colder temperatures approaching and availability of plantings, the City will need to revisit what is still needed in the spring. Please contact Nina if there are remaining items at your property if you have not already done so.
    • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


  • Construction Update - 11/3/2023

    Share Construction Update - 11/3/2023 on Facebook Share Construction Update - 11/3/2023 on Twitter Share Construction Update - 11/3/2023 on Linkedin Email Construction Update - 11/3/2023 link

    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

    • The final layer of asphalt at the intersections will occur on 11/3.
    • The final layer of asphalt is scheduled to be completed mid-week the week of 11/6.
      • Check your front door for parking and driveway access.
      • The asphalt can be driven on following final compaction rolling.


    Project Wide

    • Replacement of landscaping items impacted by construction is complete except for a few properties.
      • Due to the colder temperatures approaching and availability of plantings, the City will need to revisit what is still needed in the spring. Please contact Nina if there are remaining items at your property if you have not already done so.
    • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


  • Construction Update - 10/27/2023

    Share Construction Update - 10/27/2023 on Facebook Share Construction Update - 10/27/2023 on Twitter Share Construction Update - 10/27/2023 on Linkedin Email Construction Update - 10/27/2023 link

    Project Wide

    • Retaining wall installations are complete.
    • Replacement of landscaping items impacted by construction is complete except for a few properties.
      • Due to the colder temperatures approaching and availability of plantings, the City may need to revisit with what is still needed in the spring. Please contact Nina if there are remaining items at your property if you have not already done so.
    • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

    • The intersections are scheduled to be milled and paved with the final layer of asphalt on 11/3.
    • The final layer of asphalt is scheduled to be completed 11/7.
      • Check your front door for parking and driveway access.
      • The asphalt can be driven on following final compaction rolling.


  • Construction Update - 10/20/2023

    Share Construction Update - 10/20/2023 on Facebook Share Construction Update - 10/20/2023 on Twitter Share Construction Update - 10/20/2023 on Linkedin Email Construction Update - 10/20/2023 link

    Project Wide

    • Retaining wall installations at select locations resumed, and will be completed the week of 10/23.
    • Replacement of landscaping items impacted by construction are ongoing.
    • Irrigation repairs are nearly complete. Please contact Nina if there are remaining issues with your system if you have not already done so.
    • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

    • The final layer of asphalt is tentatively scheduled for early November.


  • Construction Update - 10/13/2023

    Share Construction Update - 10/13/2023 on Facebook Share Construction Update - 10/13/2023 on Twitter Share Construction Update - 10/13/2023 on Linkedin Email Construction Update - 10/13/2023 link

    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

    • The final layer of asphalt is tentatively scheduled for the end of October.


    Project Wide

    • Retaining wall installations at select locations are tentatively scheduled the week of 10/16.
    • Replacement of landscaping items impacted by construction are ongoing.
    • Irrigation repairs are nearly complete. Please contact Nina if there are remaining issues with your system if you have not already done so.
    • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


  • Assessment and Construction Update - 10/6/2023

    Share Assessment and Construction Update - 10/6/2023 on Facebook Share Assessment and Construction Update - 10/6/2023 on Twitter Share Assessment and Construction Update - 10/6/2023 on Linkedin Email Assessment and Construction Update - 10/6/2023 link

    Assessment Update

    On Tuesday, October 3, the City Council tabled the special assessments until October 2024. No payments will be due until October 2024.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

    • Topsoil, seeding and hydro mulching is complete. Touch ups due to rain / erosion are scheduled for the week of 10/2 and may continue into the week of 10/9.
    • The final layer of asphalt is tentatively scheduled for the end of October.


    Project Wide

    • Retaining wall installations at select locations will continue the week of 10/9.
    • Replacement of landscaping items impacted by construction are scheduled to continue the week of 10/9.
    • Signs were installed.
    • Irrigation repairs are nearly complete. Please contact Nina if there are remaining issues with your system if you have not already done so.
    • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.
Page last updated: 25 Jun 2024, 09:23 AM