Construction Update 4/21/2023

We invite you to review this document summarizing what to expect during construction.

The contractor is scheduled to begin reclaiming Morningside Road, Grimes Avenue south of Morningside Road, and West 42nd Street on 4/24 and be complete by 4/25. Reclaiming is the process of grinding the existing asphalt into a gravel base.


W. 42nd Street

  • Utility work is scheduled to continue the week of 4/24 for approximately 1 week.
  • The contractor is scheduled to begin roadway excavation and gravel installation during the week of 5/3. This process is anticipated to last approximately 1 week.
  • Concrete curb and gutter and driveway apron installation will follow the roadway excavation and are anticipated to begin during the week of 5/8.
  • Please resume checking your front door daily for time sensitive notifications.


Morningside Road and Grimes Avenue south of Morningside Road

  • In preparation for the underground utility work, removal of curb and gutter, sidewalk, and driveway aprons will begin after the reclaiming is complete.
  • The contractor is scheduled to begin setting up and testing the above ground temporary watermain during the week of 5/3.
  • During the week of 5/3 Kusske Construction will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.
  • Please resume checking your front door daily for time sensitive notifications.


Remainder of the project area

Stay tuned for updates on resuming work on sidewalk gaps, topsoil and turf, retaining walls, etc.