Construction Update - 10/13/2023

Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

  • The final layer of asphalt is tentatively scheduled for the end of October.


Project Wide

  • Retaining wall installations at select locations are tentatively scheduled the week of 10/16.
  • Replacement of landscaping items impacted by construction are ongoing.
  • Irrigation repairs are nearly complete. Please contact Nina if there are remaining issues with your system if you have not already done so.
  • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


Share Construction Update - 10/13/2023 on Facebook Share Construction Update - 10/13/2023 on Twitter Share Construction Update - 10/13/2023 on Linkedin Email Construction Update - 10/13/2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>