Construction Update 10/14/2022
Phase 2
- Remaining concrete work is anticipated to be completed during the week of 10/17.
- Areas with remaining concrete work will have the topsoil placed after the concrete is poured.
- The restoration contractor will be seeding and placing hydromulch during the week of 10/17.
- Irrigation repairs will continue through the week of 10/17.
Phase 3 – W 42nd Street
- The sanitary sewer work is complete.
- The watermain replacement work and large diameter storm sewer installation are in progress, and are anticipated to be complete by late October, early November.
- A daytime closure of W 42nd St will occur while large machines are installing the underground utilities. Please check your front door daily for time sensitive notifications related to driveway access. W 42nd St will reopen after work has concluded each day.
Phase 3 – Grimes Ave between W 42nd St & Morningside Rd AND Phase 4 – Crocker Avenue
- Curb and gutter installation is complete.
- Driveway aprons and concrete driveway replacements will be poured during the week of 10/17.
- Check your front door for time sensitive information on this work.
Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd
- Based on the Xcel Energy delays on West 42nd Street, Phase 5 will be postponed until spring 2023.