Construction Update 10/14/2022

Phase 2

  • Remaining concrete work is anticipated to be completed during the week of 10/17.
  • Areas with remaining concrete work will have the topsoil placed after the concrete is poured.
  • The restoration contractor will be seeding and placing hydromulch during the week of 10/17.
  • Irrigation repairs will continue through the week of 10/17.


Phase 3 – W 42nd Street

  • The sanitary sewer work is complete.
  • The watermain replacement work and large diameter storm sewer installation are in progress, and are anticipated to be complete by late October, early November.
  • A daytime closure of W 42nd St will occur while large machines are installing the underground utilities. Please check your front door daily for time sensitive notifications related to driveway access. W 42nd St will reopen after work has concluded each day.


Phase 3 – Grimes Ave between W 42nd St & Morningside Rd AND Phase 4 – Crocker Avenue

  • Curb and gutter installation is complete.
  • Driveway aprons and concrete driveway replacements will be poured during the week of 10/17.
  • Check your front door for time sensitive information on this work.


Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd

  • Based on the Xcel Energy delays on West 42nd Street, Phase 5 will be postponed until spring 2023.