Construction Update 10/21/22

Phase 2

  • Remaining concrete work is now anticipated to be completed during the week of 10/24.
  • Areas with remaining concrete work will have the topsoil placed after the concrete is poured.
  • Irrigation repairs will continue through the week of 10/24.


Phase 3 – W 42nd Street

  • The watermain replacement work and large diameter storm sewer installation are in progress, and are now anticipated to be complete on 11/4.
  • Crews have also begun water service replacements and will be taking homes off the temporary watermain when the water service replacements are complete. The contractor will need to access the basement of the home to finalize the transition to the permanent water line.
  • A daytime closure of W 42nd St will occur while large machines are installing the underground utilities. Please check your front door daily for time sensitive notifications related to driveway access. W 42nd St will reopen after work has concluded each day.


Phase 3 – Grimes Ave between W 42nd St & Morningside Rd AND Phase 4 – Crocker Avenue

  • Driveway aprons and concrete driveway replacements are in progress and are scheduled to be complete on 10/25.
  • Check your front door for time sensitive information on this work.
  • The first asphalt layer is scheduled to be paved by early November.


Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd – Postponed until 2023

  • Based on the Xcel Energy delays on West 42nd Street, Phase 5 will be postponed until spring 2023.