Construction Update - 10/27/2023

Project Wide

  • Retaining wall installations are complete.
  • Replacement of landscaping items impacted by construction is complete except for a few properties.
    • Due to the colder temperatures approaching and availability of plantings, the City may need to revisit with what is still needed in the spring. Please contact Nina if there are remaining items at your property if you have not already done so.
  • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

  • The intersections are scheduled to be milled and paved with the final layer of asphalt on 11/3.
  • The final layer of asphalt is scheduled to be completed 11/7.
    • Check your front door for parking and driveway access.
    • The asphalt can be driven on following final compaction rolling.


Share Construction Update - 10/27/2023 on Facebook Share Construction Update - 10/27/2023 on Twitter Share Construction Update - 10/27/2023 on Linkedin Email Construction Update - 10/27/2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>