Construction Update 10/7/2022
Phase 1
- We encourage residents to help keep the grass moist. The more you help water the higher quality turf restoration you will get.
- Tips to help grass grow can be found here.
Phase 2
- Remaining concrete work is anticipated to be completed during the week of 10/17.
- The contractor has prepared most of the phase for topsoil placement. Topsoil placement began on 9/29, and will continue through 9/30.
- Areas with remaining concrete work will have the topsoil placed after the concrete is poured.
Phase 3 – W 42nd Street
- W 42nd St utility work began on 9/28 with sanitary sewer work. This work is now scheduled to last through 10/10.
- Following the sanitary sewer work, crews will begin installing the new watermain along W 42nd St. This work is scheduled to last through the week of 10/10.
- Concurrent with the watermain work, crews will begin installing the deep and large diameter storm sewer.
- A daytime closure of W 42nd St will occur while large machines are installing the underground utilities. Please check your front door daily for time sensitive notifications related to driveway access. W 42nd St will reopen after work has concluded each day.
Phase 3 – Grimes Ave between W 42nd St & Morningside Rd
- The roadway excavation work is complete.
- Curb and gutter is scheduled to begin on 10/10.
- Driveway aprons and concrete driveway replacements will be installed following the curb and gutter during the week of 10/10.
- Check your front door for time sensitive information on this work.
Phase 4 – Crocker Avenue
- The roadway excavation work is complete.
- Curb and gutter is scheduled to begin on 10/10.
- Driveway aprons and concrete driveway replacements will be installed following the curb and gutter during the week of 10/10.
- Check your front door daily for time sensitive information on this work.
Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd – Postponed until 2023
- Based on the Xcel Energy delays on West 42nd Street, Phase 5 will be postponed until spring 2023.
Share Construction Update 10/7/2022 on Facebook
Share Construction Update 10/7/2022 on Twitter
Share Construction Update 10/7/2022 on Linkedin
Email Construction Update 10/7/2022 link
