Construction Update 10/7/2022

Phase 1

  • We encourage residents to help keep the grass moist. The more you help water the higher quality turf restoration you will get.
  • Tips to help grass grow can be found here.


Phase 2

  • Remaining concrete work is anticipated to be completed during the week of 10/17.
  • The contractor has prepared most of the phase for topsoil placement. Topsoil placement began on 9/29, and will continue through 9/30.
  • Areas with remaining concrete work will have the topsoil placed after the concrete is poured.


Phase 3 – W 42nd Street

  • W 42nd St utility work began on 9/28 with sanitary sewer work. This work is now scheduled to last through 10/10.
  • Following the sanitary sewer work, crews will begin installing the new watermain along W 42nd St. This work is scheduled to last through the week of 10/10.
  • Concurrent with the watermain work, crews will begin installing the deep and large diameter storm sewer.
  • A daytime closure of W 42nd St will occur while large machines are installing the underground utilities. Please check your front door daily for time sensitive notifications related to driveway access. W 42nd St will reopen after work has concluded each day.


Phase 3 – Grimes Ave between W 42nd St & Morningside Rd

  • The roadway excavation work is complete.
  • Curb and gutter is scheduled to begin on 10/10.
  • Driveway aprons and concrete driveway replacements will be installed following the curb and gutter during the week of 10/10.
  • Check your front door for time sensitive information on this work.


Phase 4 – Crocker Avenue

  • The roadway excavation work is complete.
  • Curb and gutter is scheduled to begin on 10/10.
  • Driveway aprons and concrete driveway replacements will be installed following the curb and gutter during the week of 10/10.
  • Check your front door daily for time sensitive information on this work.


Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd – Postponed until 2023

  • Based on the Xcel Energy delays on West 42nd Street, Phase 5 will be postponed until spring 2023.