Construction Update - 11/10/2022

Phase 3 – W 42nd Street

  • Utility work will wind down for the season during the week of 11/14.
  • Due to the low temperatures in the 10-day weather forecast, concrete curb will not be installed until 2023. Temporary asphalt pavement along West 42nd Street is scheduled to be installed before Thanksgiving.
  • Unfortunately the sidewalk won't be re-installed until 2023.


Phase 3 – Grimes Ave between W 42nd St & Morningside Rd AND Phase 4 – Crocker Avenue

  • Topsoil installation is scheduled to be complete on 11/11.
  • Asphalt driveway tie-ins are scheduled to occur on 11/11.
  • The final asphalt layer is tentatively scheduled to be paved on 11/18.


Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd – Postponed until 2023

  • Based on the Xcel Energy delays on West 42nd Street, Phase 5 will be postponed until spring 2023.