Construction Update - 11/9/2023

Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St

  • The final layer of asphalt pavement is complete.


Project Wide

  • Select pavement striping and permanent signs are scheduled to be installed the week of 11/13.
  • Sanitary sewer lining is scheduled to be completed after Thanksgiving.
  • Replacement of landscaping items impacted by construction is complete except for a few properties.
    • Due to the colder temperatures approaching and availability of plantings, the City will need to revisit what is still needed in the spring. Please contact Nina if there are remaining items at your property if you have not already done so.
  • The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.


Share Construction Update - 11/9/2023 on Facebook Share Construction Update - 11/9/2023 on Twitter Share Construction Update - 11/9/2023 on Linkedin Email Construction Update - 11/9/2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>