Construction Update 4/28/2023

As construction begins in your phase, we would like to continue to stress the importance of checking your front door daily for time sensitive notifications.


W. 42nd Street

  • Utility work is scheduled to conclude on 5/1.
  • The contractor is scheduled to begin roadway excavation and gravel installation between Crocker Ave and Grimes Ave during the week of 5/1. This process is anticipated to last approximately 1 week.
    • The contractor completed most of the roadway excavation and gravel installation west of Crocker Ave in fall 2022. Final roadway preparation for concrete curb will also occur during the week of 5/1.
  • Concrete curb and gutter and driveway apron installation along all of W. 42nd St is anticipated to begin during the week of 5/8.


Morningside Road between Oakdale and Crocker Avenues,

  • On 5/1, the contractor plans to begin water service and hydrant replacements, which are scheduled to conclude by 5/8.
  • Expect water shutoffs associated with this work.
  • The contractor will notify residents via door hanger.
  • Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.


Morningside Road between Crocker and Grimes Avenues, Grimes Avenue between Branson Street and Morningside Road

  • The contractor is scheduled to begin setting up and testing the above ground temporary watermain during the week of 5/1.
  • Expect water shutoffs associated with this work.
  • Kusske Construction will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.
  • Beginning the week of 5/8, the contractor plans to install the deep storm sewer, starting on Morningside Rd, then continuing to Grimes Ave.
  • Check your front door daily for more information regarding driveway access loss, and parking requirements.
  • Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.


Grimes Avenue between West 44th and Branson Streets

Water service work is schedule to begin mid to late May.


Remainder of the project area

Stay tuned for updates on resuming work on sidewalk gaps, topsoil, turf, retaining walls, etc.