Construction Update 5/12/2023

Check your front door daily for time sensitive notifications.


W. 42nd Street

  • Curb and gutter is complete with the exception of the few small locations.
  • Driveway aprons and concrete driveway replacements will continue the week of 5/15.
  • Residents will lose access to their driveways for 5 days while the concrete sets up. Check your front door for time sensitive information on this work.
  • Concrete sidewalk installation will continue after the apron and driveway work concludes.


Morningside Road between Oakdale and Lynn Avenues

  • Roadway excavation and preparation for concrete curb and gutter began.
  • Expect short term roadway and driveway access loss during the day while this work is occurring.


Morningside Road between Crocker and Grimes Avenues, Grimes Avenue between Branson Street and Morningside Road

  • The contractor began the deep storm sewer on Morningside Rd, and will continue to Grimes Ave. This work is anticipated to last approximately 2 weeks.
  • Check your front door daily for more information regarding driveway access loss, and parking requirements.
  • Watermain work is scheduled to begin at the end of May
  • Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.


Grimes Avenue between West 44th and Branson Streets

  • Water service work is scheduled to begin mid to late May.


Remainder of the project area

  • The irrigation contractor is scheduled to be on site beginning the week of 5/15 to restore irrigation systems.
  • Topsoil and seed re-work will begin after the irrigation systems are repaired.