Construction Update - 5/19/2023

Continue checking your front door daily for time sensitive notifications.

W. 42nd Street

  • Concrete curb and gutter, driveway aprons and concrete driveways are complete with exception of the few small locations.
  • Concrete sidewalk is complete except for the block between Kipling Ave and Grimes Ave, as well as several intersection tie-ins. This work will be completed within a few weeks.
  • Asphalt paving is tentatively scheduled to begin June 1.


Morningside Road between Crocker Ave and Grimes Ave

  • Deep storm sewer work is complete.
  • Watermain improvements are scheduled to begin the week of 5/22, with water service work to follow.
  • Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.


Grimes Avenue between Branson Street and Morningside Road

  • The contractor will begin the deep storm sewer on Grimes Ave early during the week of 5/22 and likely will conclude by 5/26.
  • Check your front door daily for more information regarding driveway access loss, and parking requirements.
  • Watermain related work is scheduled to begin at the end of May.
  • Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.


Grimes Avenue between West 44th and Branson Streets

  • Water service replacements are scheduled to begin late May.


Remainder of the project area

  • The irrigation contractor resumed restoring systems on Oakdale Ave and Branson St and will continue restoring systems in the remainder of the project area.
  • Topsoil and seed re-work will begin the week of 5/22 starting with the areas with completed irrigation.
Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>