Construction Update - 5/19/2023
Continue checking your front door daily for time sensitive notifications.
W. 42nd Street
- Concrete curb and gutter, driveway aprons and concrete driveways are complete with exception of the few small locations.
- Concrete sidewalk is complete except for the block between Kipling Ave and Grimes Ave, as well as several intersection tie-ins. This work will be completed within a few weeks.
- Asphalt paving is tentatively scheduled to begin June 1.
Morningside Road between Crocker Ave and Grimes Ave
- Deep storm sewer work is complete.
- Watermain improvements are scheduled to begin the week of 5/22, with water service work to follow.
- Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.
Grimes Avenue between Branson Street and Morningside Road
- The contractor will begin the deep storm sewer on Grimes Ave early during the week of 5/22 and likely will conclude by 5/26.
- Check your front door daily for more information regarding driveway access loss, and parking requirements.
- Watermain related work is scheduled to begin at the end of May.
- Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.
Grimes Avenue between West 44th and Branson Streets
- Water service replacements are scheduled to begin late May.
Remainder of the project area
- The irrigation contractor resumed restoring systems on Oakdale Ave and Branson St and will continue restoring systems in the remainder of the project area.
- Topsoil and seed re-work will begin the week of 5/22 starting with the areas with completed irrigation.