Construction Update 5/26/2022

Phase 1 Utility Work Continues

  • The contractor anticipates completing the water service replacement by 6/3.
  • Following the watermain work, replacement of substandard sanitary and storm sewer manholes will begin. This work is anticipated to last through 6/3.




Phase 2 to Begin Week of 5/31

  • The Contractor is scheduled to remove curb, sidewalk, and driveway ends during the week of 5/31 in preparation for the temporary above ground watermain.
  • The contractor is scheduled to begin setting up and testing the above ground temporary watermain at the end of the week of 5/31.
  • During the week of 6/6 Kusske Construction will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.


Have a Safe Memorial Day!

There will be no work on site on Memorial Day, 5/30.