Construction Update 5/26/2023

No work will occur on Memorial Day, Monday, May 29.
Please continue to check your front door daily for time sensitive notifications.
W. 42nd Street
- Roadway final grading and the first layer of asphalt paving are tentatively scheduled to begin May 30 and June 1, respectively.
- The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave
Morningside Road
- Watermain improvements are complete, water service work to follow beginning week of 5/29 between Lynn and Grimes Aves.
- Sump drain installation to continue into week of 5/29.
- Remaining sidewalk removals to begin in early June.
- Roadway excavation and gravel installation is scheduled to occur in early June after the utility work is complete.
- Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.
Grimes Avenue between West 44th Street and Morningside Road
- Deep storm sewer improvements are complete.
- Watermain and service related work is scheduled to continue the week of 5/29.
- Check your front door daily for more information regarding driveway access loss, and parking requirements.
- Sump drain installation will occur following completion of the watermain improvements.
- Roadway excavation and gravel installation is scheduled to occur in early June after the utility work is complete.
- Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.
Remainder of the project area
- The irrigation contractor resumed restoring systems within all phases of the project completed last year. Please contact Nina if your system has not been restored.
- Topsoil and seed re-work occurred in most of the areas where paving has been completed.