Construction Update 6/1/2022

Phase 1 - Utility Work Continues

  • Water services have been completed.
  • The remaining sanitary sewer and storm sewer improvements are now anticipated to continue through the week of 6/13.


Phase 2 - Removals and Temporary Watermain

  • The Contractor is scheduled to remove curb, sidewalk, and driveways on 6/3 and early in the week of 6/6.
  • The contractor is scheduled to begin setting up and testing the above ground temporary watermain during the week of 6/6.
  • During the week of 6/6 Kusske Construction will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.


Material Delays and Shortages

  • Due to nationwide shortages of building materials, the contractor is anticipating longer than average delivery times which may impact the duration of each construction phase.


Power Outage

City Staff were alerted to a power outage in the neighborhood around 8:45 AM, and power was restored around 10 AM. This was unrelated to the reconstruction activity and residents are encouraged to contact Xcel directly for updates if future power outages occur.