Construction Update 6/15/22

Phase 1 - Utility Work Continues

  • Michels is now scheduled to complete the gas main replacement in the roadway of Lynn Ave during the week of 6/20.
  • Upon completion of the gas main replacement on Lynn Ave, the contractor will begin excavating the streets and installing the new roadway base. This work is now anticipated to begin the week of 6/27.
  • Following the roadway excavation, concrete curb and gutter will be installed. This work is scheduled for late in the week of 6/27.


Phase 2 - Watermain Work to Begin

  • The contractor will continue setting up temporary water service connections through 6/17.
  • Kusske Construction will be reaching out to you to set up temporary water service. They will need access to the home to finalize the switch.
  • Watermain work is scheduled to begin on 6/21 on Oakdale Ave south of Branson.
  • The watermain work throughout the phase is scheduled to be complete the week of 6/21.