Construction Update 6/2/2023

Please continue to check your front door daily for time sensitive notifications.

W. 42nd Street

  • The first layer of asphalt paving is complete.
  • Asphalt driveway restoration is scheduled to be completed by 6/5.
  • The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave, tentatively scheduled for mid-June.

Morningside Road

  • Water service work is scheduled to begin the week of 6/5 between Lynn and Grimes Aves.
  • Sump drain installation to continue into the week of 6/5 following completion of water services.
  • Remaining sidewalk removals to begin the week of 6/5.
  • Roadway excavation and gravel installation is scheduled to begin the week of 6/12, contingent upon completion of the utility work.
  • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.


Grimes Avenue between West 44th Street and Morningside Road

  • Water service work is scheduled to continue the week of 6/5.
  • Check your front door daily for more information regarding driveway access loss, and parking requirements.
  • Sump drain installation will occur following completion of the water system improvements.
  • Roadway excavation and gravel installation is scheduled to begin the week of 6/12, contingent upon completion of the utility work.
  • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.

Remainder of the project area

  • The irrigation contractor will be back on site to continue restoring systems the week of 6/5. Please contact Nina if your system has not been restored.