W. 42nd Street
- The first layer of asphalt paving is complete.
- Asphalt driveway restoration is scheduled to be completed by 6/5.
- The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave, tentatively scheduled for mid-June.
Morningside Road
- Water service work is scheduled to begin the week of 6/5 between Lynn and Grimes Aves.
- Sump drain installation to continue into the week of 6/5 following completion of water services.
- Remaining sidewalk removals to begin the week of 6/5.
- Roadway excavation and gravel installation is scheduled to begin the week of 6/12, contingent upon completion of the utility work.
- Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.
Grimes Avenue between West 44th Street and Morningside Road
- Water service work is scheduled to continue the week of 6/5.
- Check your front door daily for more information regarding driveway access loss, and parking requirements.
- Sump drain installation will occur following completion of the water system improvements.
- Roadway excavation and gravel installation is scheduled to begin the week of 6/12, contingent upon completion of the utility work.
- Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.
Remainder of the project area
- The irrigation contractor will be back on site to continue restoring systems the week of 6/5. Please contact Nina if your system has not been restored.