Construction Update 6/23/2022

Phase 1

  • Following completion of the existing gas main removal in the roadway, Michels will install the replacement gas main, which is anticipated to conclude on 7/1.
  • Upon completion of the gas main replacement on Lynn Ave, the contractor will begin excavating the streets and installing the new roadway base. This work is still anticipated to begin the week of 6/27 – beginning on Oakdale Ave and Littel St.
  • Following the roadway excavation, concrete curb and gutter will be installed. This work is scheduled for late in the week of 6/27.


Phase 2

  • The new watermain installation began on 6/21 and is anticipated to be complete on 6/27.
  • Upon completion of the new watermain, crews will begin water service replacement work, which is scheduled to be complete during the week of 7/11. After the water services are installed, the crews will be taking homes off of the temporary water service. The contractor will need access to the home to transition water service from the temporary to the new permanent watermain.


Phase 3 – W 42nd Street

  • Work on W 42nd Street is scheduled to begin the week of 7/11 with pavement reclamation, curb & gutter removals, and driveway apron removals.
  • After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.