Construction Update 6/30/2022

Phase 1

  • Michels is scheduled to be complete with the new gas main installation in the Lynn Ave roadway on 6/30.
  • The contractor is scheduled to be complete with installing the gravel roadway base on Oakdale Ave and Littel St on 6/30. Crews will install the gravel roadway base on Lynn Ave beginning on 7/1 and concluding on 7/5.
  • Concrete curb and gutter is now anticipated to be installed late in the week of 7/5.


Phase 2 - Watermain Work to Begin

  • The new watermain has been installed and is now being tested.
  • Water service replacement work will begin during the week of 7/5 and likely conclude the week of 7/11.
  • Following the water service replacements, crews will begin storm sewer and sump drain installation.


Phase 3 - W 42nd Street

  • Work on W 42nd Street will begin the week of 7/11 with pavement reclamation, curb & gutter removals, and driveway apron removals.
  • After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.


Have a happy and safe Fourth of July!

  • There will be no work on Monday, 7/4.