Construction Update 6/30/2022

Phase 1
- Michels is scheduled to be complete with the new gas main installation in the Lynn Ave roadway on 6/30.
- The contractor is scheduled to be complete with installing the gravel roadway base on Oakdale Ave and Littel St on 6/30. Crews will install the gravel roadway base on Lynn Ave beginning on 7/1 and concluding on 7/5.
- Concrete curb and gutter is now anticipated to be installed late in the week of 7/5.
Phase 2 - Watermain Work to Begin
- The new watermain has been installed and is now being tested.
- Water service replacement work will begin during the week of 7/5 and likely conclude the week of 7/11.
- Following the water service replacements, crews will begin storm sewer and sump drain installation.
Phase 3 - W 42nd Street
- Work on W 42nd Street will begin the week of 7/11 with pavement reclamation, curb & gutter removals, and driveway apron removals.
- After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.
Have a happy and safe Fourth of July!
- There will be no work on Monday, 7/4.
Share Construction Update 6/30/2022 on Facebook
Share Construction Update 6/30/2022 on Twitter
Share Construction Update 6/30/2022 on Linkedin
Email Construction Update 6/30/2022 link