Construction Update 6/7/2022
Street Parking During Construction
- Please remember that there is no on street parking during active construction unless you are instructed to via door notification.
Phase 1 - Utility Work Continues
- Completion of the storm sewer work is anticipated for 6/10.
- Michels, on behalf of CenterPoint Energy, will be replacing the Lynn Ave gas main in the roadway during the week of 6/13.
- Upon completion of the Lynn Ave gas main replacement, the contractor will begin roadway excavation and installing the new roadway base. This work is anticipated to begin the week of 6/20.
Phase 2 - Removals and Temporary Watermain
- The concrete curb and gutter, sidewalk, and driveway removals are ongoing and anticipated to be completed on 6/9.
- The above ground temporary watermain is being installed and tested. The contractor anticipates switching homeowners to the temporary water service later this week.
- Kusske Construction will be reaching out to homeowners to set up temporary water service. They will need access to the home to finalize the switch.