Construction Update 6/9/2023

Please continue to check your front door daily for time sensitive notifications.


W. 42nd Street

  • Asphalt driveway restoration is complete.
  • The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave, tentatively scheduled to begin the week of 6/19.


Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

  • Watermain, storm sewer, and sump drain work is complete on Grimes Avenue.
  • Sump drain and storm sewer work is scheduled to conclude by 6/16 on Morningside Road.
  • Remaining Morningside Road sidewalk removals to be completed by 6/12.
  • Roadway excavation and gravel installation is scheduled to begin the week of 6/12, following completion of utility work.
  • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities, tentatively scheduled to begin the week of 6/19.
  • The first layer of asphalt paving tentatively scheduled for early July.


Remainder of the project area

  • The irrigation contractor will be back on site to continue restoring systems the week of 6/12. Please contact Nina if your system has not been restored.
  • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point. Stay tuned for further details on the Better Together Edina website for next steps.
  • Retaining walls scheduled to rebuilt starting the week of 6/12.