Construction Update - 7/14/2023

W. 42nd Street

  • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.

Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

  • The first layer of asphalt paving is complete. Final layer of asphalt tentatively scheduled for end of August.
  • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


Remainder of the project area

  • Please contact Nina if your irrigation system has not been restored.
  • Retaining wall installations will continue the week of 7/17.
  • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point, but we encourage residents to mow the weeds down. Stay tuned for further details on the Better Together Edina website for next steps.