Construction Update 7/28/2022
Phase 1 – Irrigation and Sidewalk
- During the week of 7/25, the contractor will prepare the boulevards for the new sidewalk.
- Irrigation system repairs are in progress throughout the phase, and are anticipated to be complete the week of 8/1.
- Sidewalk installation is scheduled for the week of 8/8.
- Topsoil and seeding work will follow the sidewalk work.
Phase 2 – Utility Work Complete / Street Excavation to begin 7/29
- The utility work is complete.
- The contractor will begin installing the new roadway gravel section on 7/29. This work is anticipated to last into the week of 8/1.
- Curb and Gutter is scheduled to be installed on 8/5.
- Driveway aprons and concrete driveway replacements are scheduled for the week of 8/8. Check your front door for important updates regarding loss of driveway access.
Phase 3 – W 42nd Street, Grimes Ave between W 42nd & Morningside Rd - Utility Work Begins
- The contractor began water service replacement work on Grimes Ave near Morningside Rd.
- The crews will install the storm sewer on Grimes Ave near W 42nd St early in the week of 8/1.
- Check your front door for time sensitive information on this work. The water service replacements on Grimes Ave are anticipated to be completed on 8/5.