Construction Update 7/6/2022

Phase 1

  • The contractor finished the roadway gravel base installation throughout the phase.
  • US Internet is anticipated to complete installing fiber lines on 7/7.
  • Concrete curb and gutter installation is scheduled to begin on 7/8. The concrete driveway aprons and concrete driveway replacements will follow the curb and gutter installation.


Phase 2 – Water Service Installations

  • Crews began replacing the Oakdale Ave water services on 7/5. The water service work is scheduled to be complete during the week of 7/11 throughout the phase.
  • Once the water services are installed, Kusske Construction will transition your water service from the the temporary above ground main to the permanent main. They will need to access the basement to finalize this switchover.
  • Following the water service replacements, crews will begin storm sewer and sump drain installation.


Phase 3 – W 42nd Street

  • Michels, on behalf of CenterPoint Energy, began installing a new gas main in the roadway. This work is anticipated to be completed during the week of 7/11.
  • Work on W 42nd Street will now begin the week of 7/18 with pavement reclamation, curb & gutter removals, and driveway apron removals.
  • After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.
Share Construction Update 7/6/2022 on Facebook Share Construction Update 7/6/2022 on Twitter Share Construction Update 7/6/2022 on Linkedin Email Construction Update 7/6/2022 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>