Construction Update - 7/7/2023

W. 42nd Street

  • Concrete work is complete.
  • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

  • Concrete curb and gutter and sidewalk work is complete.
  • Final roadway gravel grading will continue through 7/7.
  • The first layer of asphalt paving is tentatively scheduled for 7/10.
  • Check your front door for notifications on parking locations during paving.
  • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


Remainder of the project area

  • The irrigation contractor will be back on site to continue restoring systems the week of 7/10. Please contact Nina if your system has not been restored.
  • Retaining wall installations scheduled to begin the week of 7/10.
  • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point, but we encourage residents to mow the weeds down. Stay tuned for further details on the Better Together Edina website for next steps.