Construction Update 8/11/2022

Phase 1 Sidewalk

  • The sidewalk installation is scheduled to be complete on 8/12.
  • After the sidewalk has gained adequate strength, crews will prepare the boulevards for topsoil placement.


Phase 2 – Driveway Aprons and Concrete Driveway Work

  • Driveway aprons and concrete driveway replacements are scheduled to start on 8/11. Check your front door for a notification on this work. You will be asked to park on an adjacent street while work is occurring on your driveway.
  • The first layer of asphalt is now anticipated to be paved during the week of 8/22.


Phase 3 – W 42nd Street, Grimes Ave between W 42nd & Morningside Rd

  • Due to a rise in the groundwater level after the recent rain event, the storm sewer on Grimes Ave is delayed while the pumps at Weber Pond temporarily lower the water table.
  • Following the sewer work, crews will begin the roadway excavation in advance of concrete curb and gutter.


Phase 4 – Crocker Ave

  • Crews are scheduled to begin the utility work by replacing the sanitary sewer manholes beginning on 8/11.
  • Following the sanitary manhole work, the crews will begin replacing water services on the East side of the street in advance of the storm sewer work. Anticipate short term water shutoffs.
  • The dewatering well stations that will aid in temporarily lower the groundwater prior to the installation of the storm sewer will be installed the week of 8/15.