Construction Update 8/26/2022

Phase 1 Topsoil and Seeding

  • Topsoil installation is expected to be completed on 8/25. The contractor is aware that irrigation systems were impacted by the topsoil installation work, and irrigation repairs are expected to begin on 8/25 and continue until 8/29.
  • Seeding and hydromulching will follow the irrigation work.

Phase 2 – Paving

  • The first layer of asphalt is scheduled to be paved during the week of 8/29. Check your front door for a notification on this work.

Phase 3 – W 42nd Street, Grimes Ave between W 42nd St & Morningside Rd

  • The storm sewer work on Grimes Ave is complete.
  • Curb and Gutter was installed the week of 8/15 for most of Grimes Ave.
  • The remainder of Grimes Ave roadway excavation is now scheduled for the week of 8/29.
  • Xcel Energy is on W 42nd Street relocating power poles to allow the City’s Contractor to begin underground utility work. Xcel anticipates completing this work early in the week of 8/29.

Phase 4 – Crocker Avenue

  • Crews have begun the installation of the large diameter storm sewer. During the large diameter storm sewer installation, you can expect a short-term water shutoff while crews replace your water service pipe. This work is anticipated to last through the week of 8/29.
    1. Check your front door daily for more information regarding access loss, short term water shutoffs, and parking requirements.
Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>