Construction Update 8/5/2022
Phase 1 – Irrigation and Sidewalk
- Irrigation system repairs are scheduled to be complete on 8/5.
- The concrete sidewalk is scheduled to be installed the week of 8/8.
- Topsoil and seeding work will occur after mid-August when the seed has a higher probability of germinating due to cooler temperatures.
Phase 2 – Utility Work Complete / Curb and Gutter installation
- Concrete curb and gutter is being installed and is anticipated to be completed on 8/5.
- Driveway aprons and concrete driveway replacements are scheduled for the week of 8/8. Check your front door for a notification on this work, including temporary loss of driveway access details.
- Paving the first layer of asphalt is anticipated to occur during the week of 8/15.
Phase 3 – W 42nd St, Grimes Ave between W 42nd St & Morningside Rd
- Water service replacements are complete on Grimes Ave.
- The crews will now be installing the storm sewer and sump drain on Grimes Ave during the week of 8/8.
- The West 42nd St schedule is dependent on Xcel Energy relocating utility poles. Xcel Energy continues to delay their relocation work.
- Following the utility work, crews will begin the roadway excavation in advance of curb and gutter.
Phase 4 – Crocker Avenue
- Asphalt pavement reclamation will occur on Crocker Avenue on 8/9, weather permitting. Reclamation is the process of grinding the existing asphalt into a gravel base.
- Following the pavement reclamation, the crews will remove driveway aprons, sidewalk, and curb and gutter in preparation for the utility work.
- See the update regarding impactful utility work and resident impacts here.
Share Construction Update 8/5/2022 on Facebook
Share Construction Update 8/5/2022 on Twitter
Share Construction Update 8/5/2022 on Linkedin
Email Construction Update 8/5/2022 link
