Construction Update 8/5/2022

Phase 1 Irrigation and Sidewalk

  • Irrigation system repairs are scheduled to be complete on 8/5.
  • The concrete sidewalk is scheduled to be installed the week of 8/8.
  • Topsoil and seeding work will occur after mid-August when the seed has a higher probability of germinating due to cooler temperatures.


Phase 2 – Utility Work Complete / Curb and Gutter installation

  • Concrete curb and gutter is being installed and is anticipated to be completed on 8/5.
  • Driveway aprons and concrete driveway replacements are scheduled for the week of 8/8. Check your front door for a notification on this work, including temporary loss of driveway access details.
  • Paving the first layer of asphalt is anticipated to occur during the week of 8/15.


Phase 3 – W 42nd St, Grimes Ave between W 42nd St & Morningside Rd

  • Water service replacements are complete on Grimes Ave.
  • The crews will now be installing the storm sewer and sump drain on Grimes Ave during the week of 8/8.
  • The West 42nd St schedule is dependent on Xcel Energy relocating utility poles. Xcel Energy continues to delay their relocation work.
  • Following the utility work, crews will begin the roadway excavation in advance of curb and gutter.


Phase 4 – Crocker Avenue

  • Asphalt pavement reclamation will occur on Crocker Avenue on 8/9, weather permitting. Reclamation is the process of grinding the existing asphalt into a gravel base.
  • Following the pavement reclamation, the crews will remove driveway aprons, sidewalk, and curb and gutter in preparation for the utility work.
  • See the update regarding impactful utility work and resident impacts here.