Construction Update 9/1/2022
Phase 1 – Seeding
- The contractor has completed the repairs to the damaged irrigation systems.
- Seeding and hydromulching is scheduled for the week of 9/5. Stay tuned for tips on growing green grass.
Phase 2
- The contractor began grading and installing gravel for the sidewalk replacement. This sidewalk preparation work will be mostly complete by the end of the day on 9/2.
- Final street grading will occur on 9/6 and 9/7 in advance of the first layer of asphalt.
- The first asphalt layer is scheduled to be paved on 9/8. Check your front door for a notification of this work.
Phase 3 – W 42nd Street, Grimes Ave between W 42nd & Morningside Rd
- Grimes Avenue concrete driveway aprons are scheduled to begin late in the week of 9/5. Check your front door for a notification of this work.
- W 42nd Street utility work is anticipated to begin late in the week of 9/19 near Alden Drive.
Phase 4 – Crocker Avenue
- Crews began the large diameter storm sewer installation. During this work, you can expect a short-term water shutoff while crews replace your water service pipe. This work is now anticipated to last through the week of 9/5.
- Check your front door daily for more information regarding driveway access loss, short term water shutoffs, and parking requirements.
- Following the large diameter storm sewer installation, crews will install the city sump drain.
No Work on 9/5
- There will be no work on Labor Day (9/5). Work will resume on Tuesday, 9/6!