Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St, W 42nd St
- Topsoil installation is complete.
- Seeding and hydro mulching is complete.
- The final layer of asphalt is tentatively scheduled for the end of October.
Project Wide
- Retaining wall installations at select locations will continue the week of 9/25.
- Replacement of landscaping items impacted by construction are scheduled to continue the week of 9/25.
- Irrigation repairs are nearly complete. Please contact Nina if there are remaining issues with your system if you have not already done so.
- New topsoil, seed, and hydro mulch was installed at various locations, and will continue the week of 9/25.
- The project is nearing completion. Please contact Nina if there are any outstanding work items that need to be addressed at your property.