Construction Update 9/23/2022

Phase 1

  • We encourage residents to help keep the grass moist. The more you help water the higher quality turf restoration you will get.
  • Tips to help grass grow can be found here.


Phase 2

  • The concrete sidewalk installation is substantially complete throughout the phase. Remaining concrete walk work is scheduled to be completed after the installation of US Internet facilities.
  • Topsoil placement will follow the remaining concrete installation work.


Phase 3 – W 42nd Street

  • W 42nd St utility work will begin on 9/26 with Sanitary Sewer work. This work is scheduled to last through 9/30.
  • To maintain a dry working environment for underground utility work, the contractor has installed a dewatering system on W 42nd St to lower the groundwater. These pumps and generator will need to run continuously for an anticipated 4 weeks to facilitate the utility installation.
  • Crews have installed the temporary above ground watermain on W 42nd St, which will undergo testing before crews begin hooking homes up to temporary service.
  • Kusske construction will be reaching out to homeowners to set up temporary water service during the week of 9/26. They will need access to the home to finalize this switch to temporary water service.
  • Please check your front door daily for time sensitive notifications.


Phase 3 – Grimes Ave between W 42nd St & Morningside Rd

  • The remaining section of Grimes Ave will have roadway excavation and gravel installation during the week of 9/26.
  • Curb and gutter and driveway aprons installation will follow the roadway excavation.


Phase 4 – Crocker Avenue

  • Sump drain installation is nearly complete. The remaining sump drain will be installed on Monday, 9/26. There will be a short term (<45 minute) loss of access when the sump drain installation blocks your driveway.
  • The contractor is scheduled to begin roadway excavation and gravel installation on 9/27. This process is anticipated to last through 9/30.
  • Curb and gutter installation will follow the roadway excavation.


Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd

  • Phase 5 is tentative to begin in October. Based on the Xcel Energy delays on West 42nd Street, it's possible Phase 5 may need to be postponed until spring 2023. Many factors will contribute this, including Xcel Energy progress, weather, favorable conditions for utility work on West 42nd Street, etc. Stay tuned for future Phase 5 updates on BTE.