Construction Update 9/9/2022

Phase 1 Topsoil and Seeding

  • The contractor completed the seeding and hydromulching throughout the phase.
  • We encourage residents to help keep the grass moist. The more you help water the higher quality turf restoration you will get.
  • Tips to help grass grow can be found here.

Phase 2

  • The first layer of asphalt was paved on 9/8.
  • The sidewalk installation is scheduled to begin late in the week of 9/12.


Phase 3 – W 42nd Street, Grimes Ave between W 42nd St & Morningside Rd

  • Grimes Ave concrete work began on 9/8. Due to the rain on 9/9, crews will resume driveway apron work on 9/12.
  • W 42nd St utility work is anticipated to begin late in the week of 9/19 near Alden Drive.


Phase 4 – Crocker Avenue

  • The large diameter storm sewer installation is anticipated to be complete by 9/14.
  • Sump drain installation is scheduled to follow the storm sewer installation, and is anticipated to conclude during the week of 9/19.


Phase 5 – Morningside Road and Grimes Avenue south of Morningside Rd

  • Phase 5 is tentative to begin in October. Based on the Xcel Energy delays on West 42nd Street, it's possible Phase 5 may need to be postponed until spring 2023. Many factors will contribute this, including Xcel Energy progress, weather, favorable conditions for utility work on West 42nd Street, etc. Stay tuned for future Phase 5 updates on BTE.