Construction Update - 10/17/2025

Road Closures


Project Area

All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Alleys west of Madison Avenue

  • The first layer of paving is tentatively scheduled to be installed on Saturday, 10/18 (Weather Permitting)


Phases 1 & 2

  • The final layer of asphalt paving is is tentatively scheduled for the week of 10/20.
  • Phase 2 sod installation is complete.
  • Sod care
    • See written and video sod care tips here and here.
    • To prevent sod damage, please avoid walking on or mowing it initially.
    • The contractor will be watering for the first 60 days.
    • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


Phase 3

  • Please park vehicles in your driveways unless notified otherwise.
  • Curb and gutter installation is complete.
  • The first layer of asphalt pavement is tentatively scheduled to be installed on Saturday, 10/18, weather permitting.
  • Retaining wall installation is scheduled to begin the week of 10/20.
  • The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/20(Weather Permitting)


Tyler Court

  • Temporary replacement of concrete curb and asphalt impacted by the watermain lining will occur by the end of October.
  • The permanent and remaining roadway improvements have been postponed until 2026.


Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.