Presidents A & B Neighborhood Roadway Reconstruction

Share Presidents A & B Neighborhood Roadway Reconstruction on Facebook Share Presidents A & B Neighborhood Roadway Reconstruction on Twitter Share Presidents A & B Neighborhood Roadway Reconstruction on Linkedin Email Presidents A & B Neighborhood Roadway Reconstruction link

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
  • Construction Update – 9/12/2025

    Share Construction Update – 9/12/2025 on Facebook Share Construction Update – 9/12/2025 on Twitter Share Construction Update – 9/12/2025 on Linkedin Email Construction Update – 9/12/2025 link

    Maloney Avenue Road Closure

    • Please see the road closure update here for details.


    Project Area

    • See the construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Landscaping replacement will continue the week of 9/15.
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.
    • The final layer of asphalt paving is scheduled for late October.


    Phase 2

    • The first layer of asphalt paving is scheduled for Monday, 9/15. Please have all vehicles off the street by 7am.
    • Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/15.


    Phase 3

    • Water service installation on Jefferson Ave is complete.
    • Sump line installation will continue into the week of 9/15.
    • Watermain lining on Maloney Ave will continue into the week of 9/15.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 3 roadways are paved.


    Tyler Court

    • Watermain lining on Tyler Court will continue into the week of 9/15.


    Harrison and Tyler Avenues



  • Fall Progress Update

    Share Fall Progress Update on Facebook Share Fall Progress Update on Twitter Share Fall Progress Update on Linkedin Email Fall Progress Update link

    While progress has been made this construction season, and all the streets west of Harrison Avenue will be complete by the original November 15, 2025, completion date, it’s highly likely the streets east of Van Buren Avenue will not begin until spring 2026.

    Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area. We will continue to share updates as milestones are reached and a new 2026 completion schedule is confirmed.


  • Construction Update – 9/5/2025

    Share Construction Update – 9/5/2025 on Facebook Share Construction Update – 9/5/2025 on Twitter Share Construction Update – 9/5/2025 on Linkedin Email Construction Update – 9/5/2025 link

    Maloney Avenue Road Closure

    • Please see the road closure update here for details.


    Project Area

    • See the construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Landscaping replacement will continue the week of 9/8
    • Sod installation is complete.
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Concrete curb and gutter installation is complete. “No Parking” signs have been posted on one side of the street. Residents may park vehicles in front of their homes starting Friday, 9/5 at 6pm through the weekend. Please have all vehicles moved by 7am on Monday, 9/8.
    • Driveway access is expected to be restored by the end of the day Wednesday, 9/10.
    • The first layer of asphalt paving is scheduled for the week of 9/15.


    Phase 3

    • Water service installation on Jefferson Ave will continue the week of 9/8.
    • Watermain lining on Maloney Ave is scheduled to begin the week of 9/8.


    Tyler Court

    • Watermain lining on Tyler Court is scheduled to begin the week of 9/8.
    • Temporary water is being setup on Tyler Court in preparation for watermain lining.


  • Maloney Avenue Closure 9/3-9/19

    Share Maloney Avenue Closure 9/3-9/19 on Facebook Share Maloney Avenue Closure 9/3-9/19 on Twitter Share Maloney Avenue Closure 9/3-9/19 on Linkedin Email Maloney Avenue Closure 9/3-9/19 link

    Maloney Avenue between Washington Avenue and Tyler Court will be closed for watermain lining improvements beginning on Tuesday September 3 through September 19. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue. Please contact Brandon Freeman at 952-826-0443 or BFreeman@edinamn.gov with any questions.

  • Construction Update - 8/29/25

    Share Construction Update - 8/29/25 on Facebook Share Construction Update - 8/29/25 on Twitter Share Construction Update - 8/29/25 on Linkedin Email Construction Update - 8/29/25 link

    Construction Update – 8/29/2025


    Project Area

    • See the construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Landscaping replacement will continue the week of 9/2.
    • Sod installation is complete.
      1. See written and video sod care tips here and here.
      2. To prevent sod damage, please avoid walking on or mowing it initially.
      3. The contractor will be watering for the next 60 days.
      4. If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Concrete curb and gutter installation are scheduled to begin on Tuesday, 9/2 (Weather dependent).

    Phase 3

    • Curb and driveway apron removals are complete.
    • Installation of new water services on Washington Ave is complete.
    • Watermain installation on Jefferson Ave is complete.
    • Water service installation on Jefferson Ave is scheduled for the week of 9/2.
    • Watermain lining on Maloney Ave is scheduled to begin the week of 9/8.

    Phase 5

    • Temporary water is being setup on Tyler Ct in preparation for watermain lining that is scheduled to begin the week of 9/8.


  • Construction Update – 8/22/2025

    Share Construction Update – 8/22/2025 on Facebook Share Construction Update – 8/22/2025 on Twitter Share Construction Update – 8/22/2025 on Linkedin Email Construction Update – 8/22/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Landscaping replacement will continue the week of 8/25.
    • Sod installation is complete.
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the next 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Excavation of poor soils in preparation for the new roadway will continue into the week of 8/25.
    • To avoid extended driveway access closures around the Labor Day holiday, curb and gutter installation is tentatively rescheduled to begin the week of 9/2 (Weather dependent).


    Phase 3

    • Curb and driveway apron removals are complete.
    • Temporary water line installation is scheduled to continue into the week of 8/25.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
      • Anticipate short term water loss during this process.
    • Installation of the new water main on Washington Ave is complete.
    • Watermain installation on Jefferson Ave is scheduled to begin the week of 8/25



  • Construction Update – 8/15/2025

    Share Construction Update – 8/15/2025 on Facebook Share Construction Update – 8/15/2025 on Twitter Share Construction Update – 8/15/2025 on Linkedin Email Construction Update – 8/15/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Excavation in preparation for topsoil installation is complete.
    • Sod installation is scheduled to begin on Monday, 8/18 (Weather dependent)
    • Landscaping replacement will continue the week of 8/18.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Crews will be onsite on Saturday, 8/16 to continue excavation of poor soils in preparation for the new roadway. This work will continue the week of 8/18.
    • Sump line installation is complete.
    • Curb and gutter Installation is tentatively scheduled to begin on 8/20 (Weather dependent).


    Phase 3

    • Curb and driveway apron removals are complete.
    • Temporary water line installation is scheduled to continue into the week of 8/18.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
      • Anticipate short term water loss during this process.
    • Installation of the new water main is scheduled to begin the week of 8/18.



  • Construction Update – 8/8/2025

    Share Construction Update – 8/8/2025 on Facebook Share Construction Update – 8/8/2025 on Twitter Share Construction Update – 8/8/2025 on Linkedin Email Construction Update – 8/8/2025 link

    Project Area

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Excavation in preparation for topsoil installation will continue the week of 8/11.
    • Retaining wall installation is complete.
    • Replacement of landscape items that were removed during construction will begin the week of 8/11.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Storm sewer installation is complete.
    • Sump line installation will continue the week of 8/11.
    • Removal and replacement of poor soils in preparation for the new roadway is scheduled to begin the week of 8/11.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, and Belmore Ave will continue into the week of 8/11.
    • Temporary water line installation is scheduled to continue into the week of 8/11.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
      • Anticipate short term water loss during this process.
    • Installation of the new water main is scheduled to begin the week of 8/11.


  • Construction Update – 8/1/2025

    Share Construction Update – 8/1/2025 on Facebook Share Construction Update – 8/1/2025 on Twitter Share Construction Update – 8/1/2025 on Linkedin Email Construction Update – 8/1/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Concrete path installation along Belmore Lane is complete.
    • Excavation in preparation for topsoil installation will continue the week of 8/4.
    • Retaining wall installation is scheduled to begin the week of 8/4.


    Alleys west of Madison Avenue

    • The concrete valley gutter and curb installation is complete.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installations are complete on Monroe and Madison Ave.
    • Storm sewer and sump line installation will continue the week of 8/4.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 8/4.
    • Temporary water line installation is scheduled to continue into the week of 8/4.



  • Construction Update – 7/25/2025

    Share Construction Update – 7/25/2025 on Facebook Share Construction Update – 7/25/2025 on Twitter Share Construction Update – 7/25/2025 on Linkedin Email Construction Update – 7/25/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Asphalt driveways are complete.
    • Excavation in preparation for topsoil installation will begin the week of 7/28.
    • Installation of the concrete path along Belmore Lane is scheduled for the week of 7/28.


    Alleys west of Madison Avenue

    • A short portion of the alley will receive concrete curb and valley gutter for drainage purposes. Concrete installation is scheduled for Monday, 7/28.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installation on Monroe Ave is scheduled to continue the week of 7/28.
    • Water service installation on Madison Ave is complete.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/28.
    • Temporary water lines are scheduled to be setup the week of 7/28.



Page last updated: 12 Sep 2025, 11:57 AM