Construction Update – 10/24/2025
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Alleys west of Madison Avenue
- The first layer of asphalt is scheduled to be paved on Saturday, 10/25 (weather permitting)
Phases 1 & 2
- The final layer of asphalt paving is tentatively scheduled for the week of 11/3 (weather permitting).
- Sod care
Phase 3
- If you did NOT receive a door hanger for notifying you about driveway asphalt replacement, please DO NOT PARK ON THE STREET. Park in your driveway or garage instead.
- Street parking at this stage disrupts the ongoing work needed to complete the work in a timely manner this fall.
- Asphalt driveways are scheduled for paving Saturday, 10/25.
- If you received a door hanger notifying you about driveway asphalt replacement, please follow the parking instructions provided.
- Crews will be onsite Saturday, 10/25 preparing the topsoil for sod installation.
- Sod installation is scheduled for the week of 10/27.
- The first layer of asphalt paving is complete.
- Retaining wall installation is tentatively scheduled to begin the week of 10/27.
- The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/27 (weather permitting)
- The final layer of asphalt is scheduled to be installed the week of 11/3 (weather permitting).
Tyler Court
- Temporary replacement of curb and asphalt impacted by the watermain lining will occur by the end of October.
- The permanent and remaining roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.