Road Closures
- Washington Avenue will be CLOSED until mid-October.
- The detour route is Maloney Avenue, Blake Road and Excelsior Boulevard
- The Maloney and 3rd Street intersections will be OPEN during the closure.
- Belmore Lane between Jefferson and Adams Avenues will be closed through Monday 10/6. Please use other routes until Tuesday, 10/7.
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1 & 2
- Phase 2 sod installation will continue the week of 10/6.
- Sod care
- New retaining wall installation on Monroe Ave will continue into the week of 10/6.
- The final layer of asphalt paving is scheduled for late October.
Phase 3
- Crews will be onsite Saturday, 10/4 removing and replacing poor soils in preparation for curb and gutter.
- Storm sewer infiltration system Installation on Belmore Ln is complete.
- Curb and Gutter installation is scheduled to begin Tuesday, 10/7.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 3 roadways are paved.
Tyler Court
- Watermain lining on Tyler Court is complete.
- Temporary water is scheduled to be removed the week of 10/6.
- The roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
Share Construction Update - 10/3/2025 on Facebook
Share Construction Update - 10/3/2025 on Twitter
Share Construction Update - 10/3/2025 on Linkedin
Email Construction Update - 10/3/2025 link