Construction Update - 10/31/2025

Road Closures

Maloney Avenue between Washington Avenue and Tyler Court will be CLOSED for asphalt improvements through November 6. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue.


Project Area


All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phases 1, 2, and Alleys west of Madison Avenue

  • The final layer of asphalt paving is scheduled for Saturday, 11/1.


Phase 3

  • Asphalt driveways are complete.
  • Sod installation is scheduled to continue the week of 11/3.
  • The final layer of asphalt paving is tentatively scheduled to be completed the week of 11/3.
  • Retaining wall installation is scheduled to be completed by late November.
  • The concrete shared use path along Belmore Ln and Washington Ave is complete.
  • Tree replacements are scheduled for the week of 11/3.
  • The remaining fences that were removed during the project are scheduled to be reinstalled


Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.