Construction Update - 11/14/2025
Project Area
- All work dates below are weather permitting.
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- Grass and leaves cannot be blown or raked into the street.
- Supplemental Street sweeping increases the project costs and slows the contractors progress
- See the following link for Yard Waste guidelines(External link)
Phases 1, 2, 3
- The final layer of asphalt for Washington Ave and 3rd St is scheduled for Monday, 11/17.
- Tree replacements are scheduled for the week of 11/17.
- Retaining wall installation is scheduled to be completed by late November.
- Sod installation is complete for the season.
- Street sign installation is complete.
- The landscape contractor will be replacing impacted landscaping as long as weather permits. Any remaining work will be completed when the project resumes in the spring of 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.