Construction Update - 11/7/2025

Project Area


All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
  • Grass and leaves cannot be blown or raked into the street.
    • Supplemental Street sweeping increases the project costs and slows the contractors progress
    • See the following link for Yard Waste guidelines


Phases 1, 2, 3

  • The final layer of asphalt paving is tentatively scheduled for the week of 11/10.
  • Sod installation is scheduled to continue the week of 11/10 in Phase 3.
  • Tree replacements are scheduled for the week of 11/10.
  • Retaining wall installation is scheduled to be completed by late November.
  • Street sign installation is scheduled for the week of 11/10.


Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.