Construction Update - 4/10/26
Project Area
- All work dates below are weather permitting.
- See the construction phasing map.
Phase 4
- Vehicles cannot be parked on the street during construction.
- Temporary watermain setup will continue into the week of 4/13.
- The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Retaining wall installation is ongoing and is scheduled to be completed by mid July.
- Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.