Construction Update – 4/17/2026

Project Area

  • All work dates below are weather permitting.


Phase 4:

  • Vehicles cannot be parked on the street during construction.
  • The roads are scheduled to be reclaimed on 4/20. Reclaiming is the process of grinding the existing asphalt into a gravel base.
  • Removals including curb and gutter, driveways, and landscaping are expected to begin the week of 4/20.
  • Temporary watermain setup will continue into the week of 4/20.
    • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
  • Check your front door daily for notification of temporary driveway access or water loss.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phases 1, 2, 3

  • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
  • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.