Construction Update - 4/24/2026

Project Area

  • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
  • See the construction phasing map.
  • All work dates below are weather permitting.


Phase 4:

  • Vehicles cannot be parked on the street during construction.
  • Watermain installation is scheduled for the week of 4/27.
  • Check your front door daily for notification of temporary driveway access or water loss.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phases 1, 2, 3

  • Please park on the street if you have an alley. Alley access will be limited due to restoration work.
  • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
  • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.