Construction Update - 5/15/2026
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Sump drain installation will continue into the week of 5/18.
- Roadway excavation and soil corrections are scheduled to begin the week of 5/18.
- The watermain and storm sewer related improvements are complete.
- Check your front door daily for notification of temporary driveway access.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Remaining sod and sod replacement is complete.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.