Construction Update - 5/16/2025

PLEASE consistently check your front door daily for time sensitive notifications.


Project Area

  • See the construction phasing map here.


Phase 1

  • Vehicles cannot be parked on the street during construction.
  • Setup of the temporary above ground water main is complete.
  • The watermain subcontractor, Kusske Construction, will continue reaching out to residents via door hanger to set up temporary water service to homes. They will need access to the home to finalize the transition to the temporary watermain.
  • Check your front door daily for notification of temporary driveway access or water loss.
  • Watermain installation is scheduled to begin during the week of 5/19.


Alleys west of Madison Avenue

  • Jefferson Avenue Alley excavation and grading work is complete.
  • Washington Avenue alley excavation work is scheduled to begin on Tuesday, 5/20 and be completed by the end of the day Wednesday 5/21, weather permitting.
    • To avoid alley access issues, please park on the street in front of your homes on Washington Avenue and Adams Avenue beginning at 7 AM on 5/20 until the end of the day Wed, 5/21.
  • Alley paving will occur at a future date when the roadways are paved.


Phase 2

  • The roads are scheduled to be reclaimed on 5/19.
    1. Reclaiming is the process of grinding the existing asphalt into a gravel base.
  • Removals including curb and gutter, driveways, and landscaping will continue the week of 5/19.


CenterPoint Energy

  • CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract.
  • For additional information regarding the Maloney Avenue road closure can be found here.
  • All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.


Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.