Construction Update – 5/2/2025

As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications.


Project Area

  • See the proposed phasing map for construction.
  • Tree removals are now complete throughout the project.


Phase 1:

  • Vehicles cannot be parked on the street during construction.
  • Removals including curb and gutter, driveways, and landscaping will continue into the week of 5/5.
  • Setup of temporary watermain will begin in preparation for watermain improvements the week of 5/5.


CenterPoint Energy:

  • CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.


Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.