Construction Update - 5/22/2026

Project Area

  • No work will occur on Memorial Day, Monday, 5/25.
  • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
  • See the construction phasing map.
  • All work dates below are weather permitting.


Phase 4:

  • Vehicles cannot be parked on the street during construction.
  • Roadway excavation and soil corrections will continue through the week of 5/26.
  • Concrete curb and driveway apron installation is scheduled to begin the week of 6/2.
  • Sump drain installation is complete.
  • Check your front door daily for notification of temporary driveway access.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phases 1, 2, 3

  • Please check your front door daily the week of 5/26 for notifications of driveway access loss due to concrete warranty work.
  • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.