Construction Update - 5/23/2025

No work will occur on Memorial Day, Monday, 5/26. PLEASE consistently check your front door daily for time sensitive notifications.


Project Area

  • See the construction phasing map here.


Phase 1

  • Vehicles cannot be parked on the street during construction.
  • Watermain improvements began on Jackson Ave. Water service installation on Jackson Ave is scheduled to begin during the week of 5/26.
  • Watermain installation on Van Buren Ave is scheduled to begin the week of 5/26.
  • Check your front door daily for notification of temporary driveway access or water loss.


Alleys west of Madison Avenue

  • Washington Avenue alley excavation work has been rescheduled to begin on Tuesday, 5/27 and be completed by the end of the day Wednesday 5/28, weather permitting.
    • To avoid alley access issues, please park on the street in front of your homes on Washington Avenue and Adams Avenue beginning at 7 AM on 5/27 until the end of the day Wed, 5/28.
  • Alley paving will occur at a future date when the roadways are paved.


Phase 2

  • Curb and gutter removal is scheduled to begin the week of 5/26.


CenterPoint Energy

  • CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract.
  • For additional information regarding the Maloney Avenue road closure can be found here.
  • All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.


Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.