Construction Update - 5/8/2026
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Water service replacement and storm sewer installation is scheduled to be completed the week of 5/11.
- Sump drain installation is scheduled to begin the week of 5/11.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Remaining sod and sod replacement is expected to be installed the week of 5/11.
- Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded.