Construction Update – 5/9/2025
PLEASE consistently check your front door daily for time sensitive notifications.
Project Area
- See the construction phasing map here.
Phase 1
- Vehicles cannot be parked on the street during construction.
- Temporary watermain setup will continue into the week of 5/12.
- The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
- Check your front door daily for notification of temporary driveway access or water loss.
- Watermain installation is scheduled to begin during the week of 5/12.
Alleys west of Madison Avenue
- Pavement removals are scheduled to begin on Mon, 5/12.
- To avoid alley access issues, please park on the street in front of your homes on Jefferson Avenue and Madison Avenue beginning at 7 AM on 5/12 until the end of the day Tues, 5/13.
Phase 2
- Removals including curb and gutter, driveways, and landscaping will likely begin the week of 5/12.
CenterPoint Energy
- CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.
Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.