Construction Update - 6/19/2026
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Asphalt driveway paving is scheduled to occur the week of 6/22.
- Concrete sidewalk installation on Belmore Ln is scheduled to occur the week of 6/22.
- Topsoil installation is scheduled to begin the week of 6/22.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Share Construction Update - 6/19/2026 on Facebook
Share Construction Update - 6/19/2026 on X (formerly Twitter)
Share Construction Update - 6/19/2026 on Linkedin
Email Construction Update - 6/19/2026 link